Seminole County’s Midway Drainage Improvement Project has moved from a four-phase study recommendation to three bid-package design rows and now to eight smaller construction sub-phases. Those labels are source-dated stages, not interchangeable names.

The current project page identifies CIP 01907077, lists four phases that began construction, and separates four future phases. It does not establish that the project is finished or that completed work has produced a measured flood outcome.

How the public phase record changed

Evidence datePublic recordPhase structure or status it establishes
2021Midway Basin Engineering StudyFour recommended implementation phases; an older Phase 1 concept included a 2.7-acre pond and 36-inch trunk line
April 2025Active CIP reportBid Package 1 design 95%, Bid Package 2 design 94%, Bid Package 3 design on hold at 65%
March/May 2026Groundbreaking milestoneMarch 25 groundbreaking described as the start of the first three phases
Current page accessed August 2026Midway project pageOriginal two-package approach divided into eight sub-phases: 1A–1E and 2A–2C

Do not convert the 2021 concept into current construction scope or map “Bid Package 3” to a current phase without a County record that makes that connection.

Four phases now have construction-start records

PhaseCurrent page scopePublished amountStart and forecast
1AJack Court, Hughey, Sipes, Dixon and Water; 18- to 48-inch drainage pipe; IFAS Regional Stormwater Pond work$2.4 millionBegan March 2026; estimated early 2027 completion
1BPond near Midway Community Center and drainage infrastructure along Jitway Avenue$2.6 millionBegan April 2026; estimated early 2027 completion
1ECross drains along Hughey Street east of Sipes AvenueNot stated in the reviewed page textBegan July 2026; estimated early 2027 completion
2BBeardall and Celery drainage plus a pond near Beardall and the existing CSX ditch$5.5 millionBegan March 2026; estimated early 2027 completion

The three stated amounts add to $10.5 million:

$2.4 million + $2.6 million + $5.5 million = $10.5 million

That is a subtotal of three named phase amounts. It excludes Phase 1E and every future phase and is not a total project cost, award, or amount spent.

The milestone calls the initiative more than $30 million in proposed improvements, with federal, state, and local funding sources including the Penny Sales Tax. The proposal figure and the three-phase construction subtotal do not share a complete, comparable accounting basis, so this report does not subtract one from the other.

Source-dated updates are not current traffic proof

The current page contains a July 2026 Phase 1A update about restoration and preparation for more drainage structures. It also carries:

  • a June 2 notice describing a roughly six-week Jitway Avenue closure for Phase 1B; and
  • a July 20 notice describing daily Hughey Street closures for roughly two weeks for Phase 1E.

Those forecast windows had elapsed by the August 11 access date. Elapsed time does not prove that a road is open, closed, delayed, or complete. Use the County’s current traffic record before travel.

Four future phases remain separate

The current page describes:

  • Phase 2C in right-of-way acquisition after stated design and permitting completion;
  • Phase 2A in right-of-way acquisition;
  • Phase 1D in right-of-way acquisition; and
  • Phase 1C being prepared for construction-contract bidding after stated design, permitting, and right-of-way work.

“Design complete,” “right-of-way acquisition,” and “prepared for bidding” are different project stages. None is a construction-start or completion record.

What a later status check should collect

For a phase-level update, record the phase name, street/asset scope, source date, contract identifier, current traffic notice, construction start, accepted completion, final amount, and any measured performance report. Keep unknown fields blank rather than borrowing them from another phase or the old study.

Source and methodology

Local Service Ledger compared a 2021 County study, April 2025 CIP ledger, May 2026 milestone, and current project page on August 11, 2026. We aligned the source-specific phase structures, added only three explicitly published current phase amounts, and treated elapsed closures and forecast completions as unresolved. We did not inspect the site, audit contracts, observe flooding, or determine construction quality or completion.