Monroe Ordinance 12,293 adopts a five-year capital program for May 1, 2026 through April 30, 2031 and appropriates the first-year capital budget described in the attached program. That legislative action establishes a program and budget record. It does not, by itself, prove that every listed project has been designed, bid, awarded, started, paid, or completed.

The legislative chronology

The adopted ordinance records four process dates:

  • January 30, 2026: program submission;
  • March 10 and April 14, 2026: public hearings;
  • March 24, 2026: ordinance introduction; and
  • April 14, 2026: adoption.

The separate hearing notice adds process context. Where a notice’s fiscal-year wording or title differs from the enacted measure, preserve the conflict and use the final adopted text for the action it records.

Five records connect a program to finished work

StageRecord neededWhat it establishes
Proposed programSubmitted schedule and project listWhat was proposed at that date
Hearings and adoptionNotices, minutes, ordinanceWhat legislative action occurred
AppropriationAdopted first-year budget and amendmentsSpending authority for stated purposes
Project implementationDesign, bid, award, contract, change, payment recordsWhat happened on an individual project
CloseoutAcceptance, final amount, as-built and outcome recordsWhat was completed and at what documented result

The City Council route is useful for legislative records; Project Management is a starting point for implementation records. A project can move through these stages on a schedule different from another item in the same program.

Why this article does not state a program total

The ordinance relies on an attachment for project-level amounts. Without a verified complete attachment and any amendments, summing selected figures could omit projects, duplicate funding, or confuse multiyear planning with first-year appropriation. No total is calculated here.

The record also contains wording that should be checked against the signed ordinance and attachment before quoting an operative date or fiscal label beyond the dates stated above. Transparent uncertainty is more useful than quietly choosing one version.

Questions for one listed project

Ask for the exact program line, current appropriation, funding source, design status, procurement record, contract amount, approved changes, payments, schedule, and closeout. Identify the date of each answer. “In the capital plan” should never be rewritten as “under construction.”

Source and methodology

Local Service Ledger reviewed the ordinance, hearing record, Council route, and project-management route on August 1, 2026. We assembled four legislative dates and a five-stage verification chain. We did not calculate a program total, audit City finances, or determine the status of an individual project.