The latest update captured in Monroe’s rolling North 18th Street and Forsythe Avenue project record is dated June 1, 2026 and says construction continues. The original notice anticipated a late-spring 2026 finish, but an anticipated schedule is not a final completion statement.

Eight dated entries

The City’s rolling project notice contains the original October 31, 2025 notice and seven continuation updates:

Record dateWhat the record establishes
October 31, 2025Work was scheduled to begin November 10, weather permitting, on LA 840-6 from Hudson Lane to Bayou Desiard
November 3, 2025Updated project notice
January 6, 2026Construction continued
February 3, 2026Construction continued
March 4, 2026Construction continued
April 1, 2026Continued work; pipe repair beginning April 6 was expected to require a closure under 14 days
May 4, 2026Construction continued
June 1, 2026Construction continued

From the scheduled November 10 start to June 1 is 203 elapsed calendar days. That figure is not days worked. Weather, sequencing, closures, weekends, suspensions, and other conditions are not resolved by subtracting dates.

Do not turn a forecast into a finish

The original late-spring target records an expectation at that time. A later “construction continues” entry supersedes any assumption that the road was finished merely because the forecast window arrived. Final completion requires a later authority record.

The April pipe-repair note is also narrow: it identifies a particular activity and expected closure duration. It does not establish that the overall corridor project ended when that activity ended.

Six fields remain open in this record

The captured page does not establish:

  • actual substantial or final completion date;
  • final acceptance;
  • final contract amount and changes;
  • total days worked;
  • measured transportation or drainage outcomes; or
  • the final disposition of every lane restriction.

Readers should use Louisiana 511 for current travel conditions and the DOTD District 05 route for regional authority information. A historical article should not be used as a live closure map.

Source and methodology

Local Service Ledger reviewed the City rolling notice and two state travel/authority routes on August 1, 2026. We enumerated eight entries, counted seven continuation updates, and calculated 203 elapsed calendar days with a visible limitation. We did not visit the corridor, assess progress, calculate working days, or predict completion.