For an OUC electric customer inside City of Orlando permitting jurisdiction, rooftop solar has two public approval tracks. The City’s building and electrical permits carry the installation through final inspection; OUC then reviews an interconnection application and completes or authorizes the meter-side work.

A passed City inspection is required evidence for OUC. It is not, by itself, OUC interconnection approval or permission to operate in parallel with the grid.

Carry one address through twelve stages

StageRecordGate it proves
1. AuthorityCity-jurisdiction confirmation and OUC electric account/service addressCorrect permit and utility route
2. Usage/scopeCustomer usage history, proposed capacity, PV/battery distinctionA defined proposal, not projected savings
3. OUC design contactService address, proposed size or one-line diagram, transformer responseUtility capacity/design question opened
4. Contractor/licenseLegal installer name and current license recordIdentity only, not approval
5. Building applicationCity solar subtype, plans, scope, receipt, and permitBuilding review opened/issued
6. Electrical applicationSolar subtype, related building permit, OUC field, scope, receipt, and permitElectrical review opened/issued
7. Installation recordApproved plans, equipment schedule, changes, photos, and contractor completionWork traceable to approved scope
8. City finalsRequired inspection requests and passed results/Certificate of CompletionPermit closeout evidence for OUC
9. OUC applicationPassed permit evidence, signed itemized invoice, one-line diagram, and portal receiptInterconnection review opened
10. OUC reviewQuestions, corrections, agreement/approval, and any feeUtility decision, not installation warranty
11. Meter workExisting meter replacement or reconfiguration recordBidirectional metering step completed
12. Activation/cohortPermission/activation date, application/payment date, tariff/credit record, first bill checkOperational and billing evidence

OUC’s current rooftop-solar page starts its installer route with a proposed system-size or one-line-diagram check, then places permits, installation, final permit inspection, and interconnection application in that order.

Open both City permit records

The City building application lists Solar as a building work subtype. The electrical application separately lists Solar and includes fields for a related building permit, the electric utility, contractor, and work description.

Link them in a small crosswalk:

FieldBuilding recordElectrical recordOUC record
Job-site/service address
Applicant/installer legal name
System size
PV equipment
Battery, if any
One-line diagram revision
Permit/application numberRelated building permitInterconnection ID
Final/approval date

Resolve mismatches before the next gate. A one-line diagram revised for City comments but not updated in the OUC package can make the final public records describe different systems.

Assemble OUC’s application only after the permit evidence is ready

OUC lists these documents for its interconnection application:

  • passed City/County permit inspection or Certificate of Completion;
  • proof of purchase with customer name, service address, itemized cost, and customer signature, with battery cost separated when applicable; and
  • an electrical one-line diagram.

Save the exact versions uploaded, the portal receipt, questions, corrected documents, and final utility decision. Do not put payment-card, financing-login, or unnecessary personal data into the editorial worksheet.

OUC says the existing meter will be replaced or reconfigured for bidirectional metering after review and approval. Preserve the meter-work date and new/reconfigured meter identifier. Do not infer completion from the appearance of a meter or from solar production visible in an installer app.

Record the credit cohort without forecasting money

OUC’s page currently distinguishes two timing groups:

Completed/paid application timingCurrent page’s published treatmentPrecision limit
On or before June 30, 2025Full retail rate through June 30, 2045Must meet OUC’s cohort terms
July 1, 2025 or laterTemporary full-retail grace period, then community-solar rate through June 30, 2030, then retail levelized fuel ratePage says transition in “Fall 2026” without an exact date; rates subject to change

Record the actual completed/paid application date and the current OUC page or tariff consulted. Do not choose a fall effective date or convert the table into a savings promise.

The page also says a change in account holder can affect the later cohort and that a battery rebate has a tradeoff involving export-credit eligibility. Those are contract/tariff questions to resolve with the current OUC documents before signing; this guide does not value either choice.

Reconcile the first bill

After OUC confirms activation, preserve:

  • activation or permission date;
  • meter identifier and initial reading if supplied;
  • first complete billing period;
  • imported and exported energy fields;
  • stated credit rate/tariff reference; and
  • customer-service case for any mismatch.

One bill cannot prove annual production or payback. It can show whether the account, meter, cohort, and displayed credit fields match the retained approval record.

Source and method

Local Service Ledger reviewed OUC’s current rooftop-solar page and the City’s building and electrical forms on August 20, 2026. We mapped them into twelve evidence gates and preserved OUC’s imprecise “Fall 2026” transition wording. We did not design a system, obtain quotes, access an account, estimate production, or calculate savings.