Tampa’s project page places the Lower Peninsula Watershed Plan – Southeast Region in closeout. That is useful status information, but it does not establish final spending or prove a particular yard will no longer flood. The public records let readers connect the project to its earlier procurement without extending its claims beyond the evidence. City project record

Match the identifiers before comparing documents

The project record lists City project 1000750, department number SW40004 and contract 19-C-00059. The contract number matches the City’s 2019 design-build solicitation page.

Those identifiers are more dependable than a search for “South Tampa drainage,” which can return separate watershed work. Keep the Southeast Region name with the number whenever you save a notice or ask the City for an update.

Read the dates as different kinds of evidence

Public recordWhat it establishesWhat it does not establish
2019 solicitationProcurement history for contract 19-C-00059A currently open bid
Project page’s planned datesA planned November 2022 start and March 2026 endActual completion on either date
Closeout phase labelThe phase reported by the City when checkedFinal payment, acceptance or measured flood reduction

The solicitation page was posted in October 2019 and later updated in July 2020. Its bidding dates are historical, not a present invitation to submit a proposal.

The project page describes stormwater conveyance improvements and an outfall to Hillsborough Bay. These are the project’s stated scope and purpose; we did not inspect construction or measure drainage performance.

Use closeout to ask for the missing records

For a question about the finished work, ask which document records acceptance and whether a final cost record is available under the same identifiers. For a property-specific drainage problem, describe the location and observed condition separately from the capital project’s general goals.

Local Service Ledger joined the two City records on September 8, 2026. We did not review a final acceptance certificate, verify final expenditure or conclude that every Lower Peninsula improvement is complete.