Warren County’s US 61 overlay and Redwood retaining-wall project has moved beyond the advertisement described in our August report. The Mississippi Transportation Commission’s approved September 8, 2026 agenda, item 11, directs awards according to the August 25 letting recommendations. Its Exhibit B identifies APAC–Mississippi’s $12,178,841.45 bid for Call 03 and recommends award. Approved agenda Call 03 recommendation

That is an award-stage record, not a notice that construction or lane closures have begun. The records reviewed here do not establish a notice to proceed or a current traffic schedule.

The two jobs in Call 03

The advertised scope combines approximately 11 miles of US 61 milling and overlay with reconstruction of a retaining wall south of Redwood. The roadway limits run from 0.5 mile north of the US 80/SR 27 intersection to 0.36 mile north of SR 465 at Redwood. August 25 advertisement

WorkProject numberFederal identifier
US 61 mill and overlay108212/301000NHPP-0009-02(086)
Retaining wall south of Redwood109575/301000STBG-0009-02(094)

The bid tables shorten the project-phase numbers to 108212301 and 109575301. Keep both identifiers when asking MDOT about the combined work. The dollar amount below is for the combined call, not a separately priced wall or a per-mile paving rate.

Three bids against the revised estimate

The August 25 tabulation and September 8 Exhibit B show the same three bidder totals. Exhibit B marks the Call 03 estimate as revised August 27. Bid tabulation Revised comparison

BidderRecorded total
APAC–Mississippi, Inc.$12,178,841.45
Superior Asphalt, Inc.$14,047,653.70
Cook & Son, LLC$15,065,921.47
MDOT state estimate$11,212,013.36

LSL reproduced the comparison: $12,178,841.45 − $11,212,013.36 = $966,828.09, or 8.62% above the estimate, rounded to two decimal places. This agrees with Exhibit B. It compares the lowest listed bid with MDOT’s estimate; it is not final expenditure, a market price survey or evidence of a cost overrun during construction.

How the June record fits

The June 5 advertisement already listed the overlay project, 108212301, with the same approximate corridor limits. The August 25 Call 03 paired that overlay with the retaining wall. These two appearances are part of one project’s record history, not two separate eleven-mile paving projects. The reviewed records do not explain why the earlier advertisement was followed by the combined call. June advertisement

An older wall record has a different phase suffix: the FY 2025 annual report, PDF page 119, lists 109575/101000 as engineering work to investigate the retaining wall, install instrumentation and recommend repairs. That is distinct from the 301000 construction phase in the letting. Do not add its expenditure to the bid total and call the sum a contract value. Engineering-phase record

Checking work-zone information

For a travel or access question, give MDOT the route, Warren County and both Call 03 identifiers, then ask for the applicable current traffic notice. Use the Commission record page for later decisions, not as a substitute for a work-zone notice. This report does not identify affected parcels or tell drivers which lanes are open.

LSL compared the two advertisements, all three tabulation pages, the September 8 approved award item, its project-specific exhibit and the annual report’s Warren County engineering row on September 13, 2026. The estimate comparison is our calculation; the project scope and bid totals are MDOT records. No site visit, contractor interview or business endorsement occurred. This report consolidates our earlier standalone June US 61 overlay article so the same project has one maintained account.