An Edgewood home-project file can cross two governments before construction starts. The City reviews local requirements; Orange County issues the building permit and conducts building inspections. Treating the City stamp as the permit—or filing County records without the City decision—breaks that chain.

Use a custody ledger

StageRecord ownerSave this evidence
Local intakeEdgewoodSubmitted plans, completeness messages, invoices, and receipts
Local decisionEdgewoodThe signed and stamped approval and every attached condition
Permit intakeOrange CountyFast Track submission receipt and the exact stamped plan set sent onward
Permit issuanceOrange CountyPermit number, issued documents, and named subpermits
Field workOrange County, with any stated City roleInspection requests, results, corrections, and reinspection records
CloseoutBoth, when applicableCounty completion record and any Edgewood engineering final

The City overview says most applicants submit electronically to Edgewood first and then take the approved plans to Orange County Fast Track. It also identifies a narrower route in which roofing, plumbing, or electrical subpermits may go directly to the County. Do not assume that exception applies: retain the written routing instruction for the actual scope.

Keep project-class money separate

The single-family page identifies a $500 nonrefundable City application charge and a $2,500 pass-through deposit for that project class. The general page describes consultant costs that vary. Record each payment by its label—fee, deposit, or consultant charge—and retain the final reconciliation. A deposit is not automatically a project cost, and the single-family intake is not a universal price list.

Before work begins, compare the County permit plan set with Edgewood’s stamped version. At closeout, check whether a City engineering final was assigned in addition to County inspections. The result should be one chronological record with two clearly named authorities, not a blended approval.